| CONSTRUCTION OF 3 NOS 6” X 6KM BULKLINES AND 1 NO. 4” X 6KM TESTLINE FROM OBI ANYIMA FIELD MANIFOLD TO EARLY PRODUCTION FACILITY AT OWA ALIDINMA |
PAN OCEAN OIL CORP. (NIG.) LTD |
CONSTRUCTION OF 3 NOS 6” X 6KM BULKLINES AND 1 NO. 4” X 6KM TESTLINE FROM OBI ANYIMA FIELD MANIFOLD TO EARLY PRODUCTION FACILITY AT OWA ALIDINMA |
| EPCC OF 6” X 15KM DUAL PIPELINE PROJECT FROM OWA – ALADINMA TO OGHAREFE FLOWSTATION, DELTA STATE (2013 – 2014) |
PAN OCEAN OIL CORP. (NIG.) LTD |
CONSTRUCTION OF 6” X 15KM PIPELINE FROM OWA ALADINMA TO OGHAREFE FLOWSTATION. |
| EPCC OF 10” X 15KM DUAL PIPELINE PROJECT FROM OWA – ALADINMA TO OGHAREFE FLOWSTATION, DELTA STATE (2013 – 2014) |
PAN OCEAN OIL CORP. (NIG.) LTD |
CONSTRUCTION OF 10” X 15KM DUAL PIPELINE FROM OWA ALADINMA TO OGHAREFE FLOWSTATION. |
| CONSTRUCTION OF 1 X 4 INCHE X 6.0KM PIPELINE FROM UQUO CENTRAL PROCESSING FACILITIES (CPF) TO THE FUN MANIFOLD (UQUO MARGINAL FIELD, EKET, AKWA IBOM STATE. OML-013)
FEB. - NOV. 2011
|
FRONTIER OIL LIMITED |
CONST. OF 1 X 4 INCHE X 6.0KM PIPELINE FROM CENTRAL PROCESSING FACILITIES(CPF) TO CUSTODY TRANSFER FACILITIES (CTF FUN MANIFOLD) Contract No FOL-E/2010/FE-011 |
| CONSTRUCTION OF 1 X 6 INCHE X 6.0KM PIPELINE FROM UQUO CENTRAL PROCESSING FACILITIES (CPF) TO THE FUN MANIFOLD (UQUO MARGINAL FIELD, EKET, AKWA IBOM STATE. OML-013)
FEB. – NOV. 2011
|
SEPTA ENERGY LIMITED / FRONTIER OIL LIMITED |
CONST. OF 1 X 6 INCHE X 6.0KM PIPELINE FROM CENTRAL PROCESSING FACILITIES(CPF) TO CUSTODY TRANSFER FACILITIES (CTF FUN MANIFOLD) Contract No FOL-E/2010/FE-011b |